FAT and SAT Testing: A Practical Checklist for Control System Commissioning

A new control system can look perfect on paper and still fail on startup day. Wrong I/O addresses, missing alarms and untested interlocks are often found too late, when the plant is waiting to run.

Two tests catch most of these problems early: the Factory Acceptance Test (FAT) and the Site Acceptance Test (SAT). The international standard IEC 62381 defines both tests for automation systems in the process industry.

This guide explains the difference between FAT and SAT and gives a simple checklist for each.

What Is a Factory Acceptance Test (FAT)?

A FAT is done before the system ships to site. The integrator or panel builder tests the control panels, PLC program and HMI screens with the owner present.

The goal is simple: prove that the system works as specified before it leaves the shop. Problems found here are faster and cheaper to fix than problems found in the field.

What Is a Site Acceptance Test (SAT)?

A SAT is done after the system is installed at the plant. It proves the system works with the real field devices, wiring, utilities and process conditions.

The SAT confirms what the FAT could not, such as real sensor signals, motor rotation, valve travel and communication with other plant systems.

FAT vs SAT: Key Differences

FATSAT
WhereIntegrator’s shop or factoryCustomer’s plant site
WhenBefore shippingAfter installation
Field devicesSimulatedReal
Main goalProve the design and logicProve the installed system works in the process
Who attendsIntegrator and ownerIntegrator, owner, operators and maintenance

FAT Checklist

  • Approved drawings, I/O list and functional specification are on hand
  • Panel inspection: labels, wiring, terminations and grounding
  • Power-up and power-loss test
  • Every I/O point tested with simulated signals
  • Control logic and sequences tested against the specification
  • Interlocks and permissives tested
  • Alarms tested and alarm text checked
  • HMI screens, navigation and user access checked
  • Communication with drives, networks and other devices tested
  • Punch list recorded and signed off

SAT Checklist

  • Installation check: panels, field wiring and grounding
  • Loop checks from field device to HMI
  • Motor rotation and valve stroke checks
  • Instrument ranges and scaling confirmed
  • Safety functions and emergency stops tested
  • Integration with SCADA, historian or other plant systems tested
  • Sequences tested with the real process
  • Operator training completed
  • Final program backups saved
  • As-built drawings and documents handed over

Tips for a Smooth FAT and SAT

  1. Agree on test procedures early. Both sides should approve the test plan before the FAT.
  2. Bring operators to the FAT. They catch HMI and workflow issues engineers often miss.
  3. Keep one punch list. Track every open item from FAT to SAT in one place.
  4. Do not skip the SAT. A good FAT does not prove field wiring or real process behavior.
  5. Back up at the end. Save the final PLC and HMI programs after the SAT, not before.

How Reliamation Can Help

Reliamation supports projects from design through startup. Our team handles FAT, SAT, loop checks, commissioning and operator training for plants in Texas and beyond. See our Plant Start-up & Commissioning services.

Need Help Planning a Plant Startup?

Contact Reliamation to talk about your commissioning plan.

FAQ

Frequently Asked Questions

Get answers to common questions about industrial automation, PLC migration, HMI, SCADA, and control-system integration.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top
Get More Information